
Drilled Mini Piling :
Leighstone Court stabilisation
Drilled
mini piling design : Branlows
were responsible for the detailed drilled mini piling design and installation of all
drilled mini piling
works which comprised, 70 x 220mm diameter drilled
minipiles socketed into sandstone
at depths of up to 31 m. The majority of the drilled mini piles were cored
through the existing structural raft/floor slab.
Other drilled mini piles were supporting new reinforced concrete ground beams at
critical corner location. Drilled
mini piling : The
existing 3 storey flats were constructed 30 years ago, built over vibro
column foundations.
Due to the depth and extreme looseness of the fill
material, the vibro flotation failed causing subsidence to the flats.
In
1990, the insurance company responsible for the property brought in a
specialist piling contractor to stabilise the building using a system of
piling and overlying slabs. Although
the slab was installed adequately, unfortunately, the piles were not
taken down to bedrock. Where these pile depths have been determined
through testing, they were found to be in the 6-1 Urn depth range.
With
rock head varying on the site between 13-26 metres, the stabilisation
works exacerbated the problem by increasing the dead load on the loose
fill, triggering off further consolidation settlements. Exceptionally
loose fill was encountered in the infilled quarry above rockhead, with N
values normally below 5 and in some areas in the 1 -2 range. Rockhead
was found to directly underly the fill material in most areas although
in some instances massive sandstone boulders were encountered just above
rockhead. The
majority of the piles were installed within the existing building with
a limited headroom of 2.5 metres. The
new works were undertaken within the four ground floor flats, foyer and
stairwell areas. The presence of numerous internal walls, door openings
etc made access extremely difficult. Drilled
minipile
220mm
diameter : were used throughout and the
mini piles were
installed by employing an eccentric overburden drilling system to take
the permanent 220mm diameter casing a distance of approximately 1 metre
into solid bedrock. A
down-the-hole hammer of 170mm diameter was then used to form rock
sockets of average depths of 4-5 metres. Safe
working loads of 320Kn were adopted and the permanent steel cased piles
were infilled using tremmieing techniques utilising a cement/pfa C40
grout mix. Reinforcement comprised a full length 25mm Dywidag bar
with full strength couplers. Problem
ground, very
loose fill material, with N values commonly less than 5, were
encountered in the upper 20 metres; in some areas the fill was present
directly over the sandstone formation. In other areas where the
sandstone formation dipped to depths of 26 metres, large rock boulders
were encountered in the base of the old quarry. This caused difficulties drilling
for the piles as it appeared in numerous instances that natural bedrock
had been encountered. On
commencement of the final rock socketing, we found the works
for the piles went back into loose fill material below the sandstone boulders which
necessitated reconnecting the overburden mini pile drilling system and taking the
permanent steel casing deeper into the underlying competent bedrock. Twelve families had to be evacuated from the flats and
were placed in alternative accommodation. These costs alone,
together with the inconvenience to the residents, demanded the
shortest possible time
scale
for the works on site. Due to the
restricted access and limited headroom on the site, static load pile testing was not undertaken but the mini piles had two dynamic load tests
carried
out using Capwap analysis. Settlements of 3.0mm and 3.07mm were
recorded at working load and settlements of 4.51mm and 4.28mm were
recorded at one and a half times working load on the two test piles.
On
removal of the load, a 95% recovery in the pile deflection was observed,
indicating that the drilled pile settlement was of a purely elastic nature.
| Services
|
General Information
|
|